Ready for Teachers and Students! ~ End-August
Classrooms are ready for teachers' finishing touches!
Looking from the bus path.
Rear view of the Bear Dens.
Bear Den ramp hallway.
View of the hallway leading to the classrooms.
Finishing Touches ~ Mid-August
This image shows some of the classroom interior finishes including carpet, white boards, projector, lights, etc.
Hallway ramp up to classrooms (looking from former bus shelter toward modular). Contractors complete prepping, paint, ceiling, and window installation.
Vestibule installation - End July
Vestibule exterior.
Vestibule interior.
Connecting the Modular Ramp to the Building - Mid-July
Contractors work on the area connecting to the modular ramp to the bus door shelter.
Contractors complete the cement base leading to ramp.
Building the ramp.
Modular Placement - End June
Holes for Supporting Footers - 6-18-19
Fencing Installed - 6-4-19
Fencing was installed around the area where modulars will be positioned.
Materials for the "Bear Dens" will be delivered and placed within the confines of the fencing in the coming weeks.